Quotify worksheets

Estimate and quote comparison worksheet

Hypothetical extension comparison, not a customer estimate or a market-price benchmark. Base costs are ex VAT. The £1,500 difference identifies review questions; it does not establish accuracy or extra profit.

Download blank CSVDownload completed CSV

E01: Enabling

Reference
E01
Work package
Enabling
Scope and document basis
Illustrative extension pack A03
Labour GBP
6000
Materials GBP
1000
Plant GBP
2000
Subcontract GBP
3000
Base cost GBP
12000
Existing comparable cost GBP
12500
Difference GBP
-500
Review decision
Check disposal and temporary support basis

E02: Structure and envelope

Reference
E02
Work package
Structure and envelope
Scope and document basis
Illustrative extension pack A03
Labour GBP
32000
Materials GBP
40000
Plant GBP
4000
Subcontract GBP
16000
Base cost GBP
92000
Existing comparable cost GBP
90000
Difference GBP
2000
Review decision
Review wall build-up and glazing allowances

E03: Services

Reference
E03
Work package
Services
Scope and document basis
Illustrative services allowance
Labour GBP
0
Materials GBP
0
Plant GBP
0
Subcontract GBP
26000
Base cost GBP
26000
Existing comparable cost GBP
26000
Difference GBP
0
Review decision
Confirm both figures include the same point schedule

E04: Finishes and external works

Reference
E04
Work package
Finishes and external works
Scope and document basis
Illustrative finishes schedule
Labour GBP
9000
Materials GBP
7000
Plant GBP
1000
Subcontract GBP
5000
Base cost GBP
22000
Existing comparable cost GBP
22000
Difference GBP
0
Review decision
Check client selections and access

E05: Preliminaries

Reference
E05
Work package
Preliminaries
Scope and document basis
Illustrative twelve-week programme
Labour GBP
6000
Materials GBP
1000
Plant GBP
1000
Subcontract GBP
2000
Base cost GBP
10000
Existing comparable cost GBP
10000
Difference GBP
0
Review decision
Confirm supervision and welfare duration

TOTAL: Base cost

Reference
TOTAL
Work package
Base cost
Scope and document basis
Sum only E01 to E05
Labour GBP
53000
Materials GBP
49000
Plant GBP
8000
Subcontract GBP
52000
Base cost GBP
162000
Existing comparable cost GBP
160500
Difference GBP
1500
Review decision
Price difference requires review; it is not saved profit

Use it on your project

  1. Keep each original estimate and its document register. Copy comparable package costs into separate columns.
  2. Check inclusions, exclusions, allowances, revisions and tax before comparing amounts. A matching total alone does not establish matching scope.
  3. Add the labour, materials, plant and subcontract amounts once for each package. Keep project risk and overhead/profit separate from base cost.
  4. Record the reason for each material difference and its remaining action. Calculate the totals in your working spreadsheet, then use the price-review checklist before issue.

Read the matching guide · Open the Academy task